Construction Complete!

Thanks Maple Hollow residents for being patient with this major construction project. Completed: Thursday Oct. 15, 2015

All Construction images from 09/09 to 10/14


Archived Instructions

Keep posted to this website construction page, newsletter (sign up at the bottom of this page), Twitter feed, and our Facebook page for important parking instructions. The schedule is constantly changing due to weather and construction progress on other areas. We are actively working with the contractor to make sure we communicate information as it becomes available.

Driveway and road work on Tanager Ct. and Creekside Ct. are in full swing. Parts of the street and driveways will be inaccessible, and you may need to park on the streets of Tanager Ct. or Creekside Ct. for a few nights. To ensure parking for everyone, we are trying to split work between the two streets. However, this may not be enough and we need your help. We are requesting all tenants to find a neighbor (i.e. “buddy”) with whom you can share your driveway for the night. In turn, they will share when your driveway is blocked.

Parking on Swift Rd and Lynn Rd are not permitted. Violators may be ticketed for illegal parking by DuPage county sheriff.

Schedule subject to change due to weather and construction progress on other areas.

Archived Schedule

Wednesday October 14th- Tanager & Creekside

Street sealcoating will affect all units. Both streets will be closed for 24 hours.

Please have your cars out of the driveway, guest parking, and streets by 7:00 A.M. Do not park around cul-de-sac, grass, or the street as cars will prevent contractors from doing work. Cars parked in driveways will be blocked in for 24 hours. Violators will be fined and towed if they are blocking the road. Residents may return after street barriers are removed 24 hours later.

Tanager parking is with DarusSalam Foundation Mosque (gravel area), and Creekside parking arrangements is with Divine Mercy Polish Mission Church. Please park at your designated location, as everyone parking in one lot will overwhelm the lot and make future permission difficult. Please park at those locations on Wednesday only, then move cars back to your own unit on Thursday. Only a part of Lynn Rd. is permitted to park only on Wednesday and Thursday, see map below. Do not park on Swift Road, as violators may be ticketed by the DuPage County sheriff. We do not have permission to park at the Willow Lake Apartments.

Tues., Oct. 6th, – Creekside
Driveway top coat and street repairs

Driveways will not be accessible for 24 hours to allow asphalt top coat to cure. Do not park around  cul-de-sac, on unfinished driveways, or the street as it prevents the semi-trucks and equipment from doing work. Violators will be stickered or towed if they are blocking the road. Residents may park in front of their own driveways after 7 P.M. and return on the driveway when string and reflective tape are removed.

Garbage pickup will remain as scheduled, with the construction crew moving for Waste Management. Place all bins and cans on grassy surface if possible.

Parking arrangements have been made with Willow Lake Apartments. Please park there temporarily from 7 A.M. to 7 P.M. on Tuesday only, then move cars in front of your own unit after 7 P.M. Please ensure your cars are not blocking the other cars, or entry to homeowner driveways.  Do not park in front of hydrants and stop signs. Do not park on Lynn or Swift Road, as violators may be ticketed by the DuPage County sheriff.

Mon., Oct. 5th – Tanager
Driveway top coat and street repairs

Driveways will not be accessible for 24 hours to allow asphalt top coat to cure. Do not park around  cul-de-sac, on driveways, grass, or the street as it prevents the semi-trucks and equipment from doing work. Violators will be stickered or towed if they are blocking the road. Residents may park in front of their own driveways after 7 P.M. and return on the driveway when string and reflective tape are removed.

Parking arrangements have been made with the Divine Mercy Polish Mission Church and DarusSalam Foundation Mosque gravel area. Please park there temporarily from 7 A.M. to 7 P.M. on Monday only, then move cars in front of your own unit after 7 P.M. Please ensure your cars are not blocking the other cars, or entry to homeowner driveways.  Do not park in front of hydrants and stop signs. Do not park on Lynn or Swift Road, as violators may be ticketed by the DuPage County sheriff.

Garbage pickup will remain as scheduled, move cars off the street for Waste Management Tuesday morning.

Tues. and Wed., Sept. 29th and 30th, – Tanager & Creekside

Driveway removal of both streets. Removal will be done this week, with only binder (bottom layer asphalt) applied to all units. Move cars into garage or guest parking to allow removal. You may park overnight when the binder (bottom layer) is applied.

 Sat., Sept. 26th – Creekside

Driveway replacement on following units:
1N533,1N535,1N537,1N539,1N541,1N543,
1N557,1N555,1N553,1N551,1N549,1N547
Guest parking next to 1N557 will be under construction and also unavailable.

Thr., Sept. 17th – Creekside

Curb removal on following units:
1N532,1N530,1N528,1N526,1N524

Wed., Sept. 16th – Tanager

Curb removal on following units:
21W475,21W473,21W471,
21W469,21W467,21W465

Tues., Sept. 15th – Creekside

Curb removal on following units:
1N569,1N567,1N565,1N563
1N550,1N552,1N554,1N556,1N558,1N560
1N540,1N538,1N536,1N534
Guest parking next to 1N534 will be under construction and also unavailable.

Mon., Sept. 14th – Tanager

Curb removal on following units:
21W509,21W507,21W505,21W487,21W485,21W483,
21W526,21W524,21W522,21W520,21W518,21W516
Guest parking next to 21W483 will be under construction and also unavailable.

Thrs., Sept. 10th | Fri., Sept. 11 – Creekside

Curb removal on following units:
1N533,1N535,1N537,1N539,1N541,1N543,
1N557,1N555,1N553,1N551,1N549,1N547
Guest parking next to 1N557 will be under construction and also unavailable.
1N559 and 1N561 were added last minute (our apologies for the lack of communication)

Wed., Sept. 9th – Tanager

Curb removal on following units:
21W486, 21W484, 21W482, 21W480, 21W478,
21W466, 21W464, 21W462, 21W460
Guest parking between the two areas will also be unavailable.

Construction